Trans Mountain Corp. has completed the first part of its plan to boost the capacity of its recently twinned pipeline from Alberta to Burnaby, just at the right time to cash in on market dynamics.
Article content
The company embarked on the first of the two-step “optimization plan,” in June shortly after receiving approval from the Canada Energy Regulator and had its new equipment commissioned by October. It adds 90,000 barrels a day, bringing its capacity to 980,000 barrels a day.
Article content
Article content
Advertisement 1
Story continues below
Article content
Calgary energy economist Richard Masson said the additional capacity is coming on line just as Trans Mountain has had to start rationing access to its pipeline.
Article content
Article content
Reuters reported that Trans Mountain had reached capacity in June and had to begin apportioning, or rationing. In October, the rating agency S&P Global reported that the Trans Mountain pipeline was oversubscribed by seven per cent for that month.
Article content
So, “it’s been really timely,” said Masson, an executive fellow at the University of Calgary’s school of public policy, because the Asian buyers of Western Canadian Select, the blend of bitumen and diluent from the oilsands, are willing to pay a premium for the product at the same time U.S. buyers are demanding steep discounts for Canadian heavy crude.
Article content
“If you can get down Trans Mountain and sell into Asia, it’s much more profitable right now than it had been,” Masson said. “So yeah, it’s good that they’ve got that approval because that will help balance the overall market.”
Article content
Asian demand for oil from Trans Mountain has increased since the U.S. war with Iran choked shipments through the Strait of Hormuz. It also coincides with Prime Minister Mark Carney’s desire to increase Canada’s non-U. S. exports.
Article content
Advertisement 2
Story continues below
Article content
Trans Mountain refers to the first step in its “optimization” as the drag reducing agent project, which involved installing equipment at 16 pump stations to inject a special fluid that reduces internal friction in the lines.
Article content
Read More
-
Amazon forced into first North American union pact, in B.C.
-
Despite Canada-U.S. tensions, this West Coast route as old as the gold rush endures
-
Advertisement 1
Story continues below
Article content
CEO Mike Davies said the work shows how “targeted improvements to existing infrastructure” can build on the foundation of its existing infrastructure to increase capacity.
Article content
“With construction now completed, DRA (drag-reducing-agent) facilities are poised to play an important role in supporting the efficient operation of the Trans Mountain pipeline system,” Davies said.
Article content
Masson said Trans Mountain’s capacity increase helps justify the next step of its optimization, an up-to-$4-billion project to add pumping stations and a strategically located pipeline loop near Kamloops, which would increase its capacity by another 210,000 barrels a day.
Article content
Trans Mountain filed its application for that part of the project in August and the company’s intent is to have the additional facilities in place by the end of 2028.
Article content
Masson added that the additional capacity “is meaningful” for an Alberta oil sector angling to expand, especially while the proposed one-million-barrels-per day Pacific Link pipeline proposal is working through a business case to justify its estimated $44 billion cost.